Mumbai-Ahmedabad bullet train project: How much excavation work is done on Bandra Kurla Complex?

Around 76 per cent of the excavation work has been completed on the Mumbai bullet train station located at 'Bandra Kurla Complex' (BKC), which is the only underground station on the Mumbai-Ahmedabad High-Speed Rail Corridor. According to the official report, 14.2 lakh cubic metres of the excavation work has been completed. 18.7 lakh cubic metres of earthwork must be excavated from this site.